If the daily scrum happens every two or three days (if the frequency is lowered) that can lead to: -the opportunities to inspect and adapt the Sprint Backlog can be lost - Impediments are raised and resolved more slowly -too much work is spent updating the scrum board before the meeting -the Sprint plan becomes inaccurate.